Main Roads WA High Street Upgrade
Consultation has concluded
The intersection of High Street and Stirling Highway needs major improvements to make it safer and reduce traffic congestion.
Background
The proposed $118 million High Street Upgrade from Carrington Street to Stirling Highway project is jointly funded by the Australian ($73.62 million) and State ($44.38 million) governments and is part of the road and rail infrastructure package to improve Perth’s transport network.
The initial concept for High Street, released in 2013, is no longer the preferred option. In March 2018 Main Roads WA released a new draft concept plan for the upgrade of High Street.
Main Roads Consultation
The City of Fremantle encourages all who are impacted by or interested in the upgrade of High Street to take part in engagement opportunities during the consultation period.
An updated draft concept was prepared taking into consideration feedback from the community and City of Fremantle, see the August 2018 newsletter for further information.
Find out more
To find out more and this Main Roads project check on further updates, visit the Main Roads website.
The intersection of High Street and Stirling Highway needs major improvements to make it safer and reduce traffic congestion.
Background
The proposed $118 million High Street Upgrade from Carrington Street to Stirling Highway project is jointly funded by the Australian ($73.62 million) and State ($44.38 million) governments and is part of the road and rail infrastructure package to improve Perth’s transport network.
The initial concept for High Street, released in 2013, is no longer the preferred option. In March 2018 Main Roads WA released a new draft concept plan for the upgrade of High Street.
Main Roads Consultation
The City of Fremantle encourages all who are impacted by or interested in the upgrade of High Street to take part in engagement opportunities during the consultation period.
An updated draft concept was prepared taking into consideration feedback from the community and City of Fremantle, see the August 2018 newsletter for further information.
Find out more
To find out more and this Main Roads project check on further updates, visit the Main Roads website.
-
Release of Golf Course Concept
Share Release of Golf Course Concept on Facebook Share Release of Golf Course Concept on Twitter Share Release of Golf Course Concept on Linkedin Email Release of Golf Course Concept linkTo achieve a quality outcome for the golf course realignment (required as a result of the Main Roads WA High St project) the City of Fremantle engaged highly respected specialist golf course designers to reconfigure the course around some challenging constraints.
Over the past 5 months 2 public workshops have been held with the golf club members to present options, which provided the opportunity for input and feedback. The City’s team and the Golf Course Designers met with the lessee numerous times and tested many options to find the best solution.A preferred concept has been endorsed by the lessee and is available to download from the project page on the City's website here: www.fremantle.wa.gov.au/fremantle-public-golf-course-and-clubhouse-facility
Consultation has concludedTo achieve a quality outcome for the golf course realignment (required as a result of the Main Roads WA High St project) the City of Fremantle engaged highly respected specialist golf course designers to reconfigure the course around some challenging constraints.
Over the past 5 months 2 public workshops have been held with the golf club members to present options, which provided the opportunity for input and feedback. The City’s team and the Golf Course Designers met with the lessee numerous times and tested many options to find the best solution.A preferred concept has been endorsed by the lessee and is available to download from the project page on the City's website here: www.fremantle.wa.gov.au/fremantle-public-golf-course-and-clubhouse-facility
-
Subscribe for Main Roads Updates
Share Subscribe for Main Roads Updates on Facebook Share Subscribe for Main Roads Updates on Twitter Share Subscribe for Main Roads Updates on Linkedin Email Subscribe for Main Roads Updates linkContact Main Roads WA
If you have any questions or concerns, please phone 138 138 or email enquiries@mainroads.wa.gov.au .
More project information is also available at project.mainroads.wa.gov.au/home
Subscribe for Further Updates
You can subscribe to receive ongoing updates from Main Roads WA on this project: webcd.mainroads.wa.gov.au/cn/azvoz/projects
Consultation has concludedContact Main Roads WA
If you have any questions or concerns, please phone 138 138 or email enquiries@mainroads.wa.gov.au .
More project information is also available at project.mainroads.wa.gov.au/home
Subscribe for Further Updates
You can subscribe to receive ongoing updates from Main Roads WA on this project: webcd.mainroads.wa.gov.au/cn/azvoz/projects
-
New clubhouse and community building for golf course and Boo Park
Share New clubhouse and community building for golf course and Boo Park on Facebook Share New clubhouse and community building for golf course and Boo Park on Twitter Share New clubhouse and community building for golf course and Boo Park on Linkedin Email New clubhouse and community building for golf course and Boo Park linkAs part of the High Street project Main Roads will fund a program of accommodation works including the temporary reconfiguration of the golf course to ensure it can remain open for the majority of the construction period and some long term improvements, including the permanent realignment and redesign of the course, a new club house and a suitable replacement for the community facility.
The council’s Finance, Policy, Operations and Legislation Committee has authorised City officers to progress with the design of a co-located clubhouse and community facility.
View the full media release by clicking here or visiting: www.fremantle.wa.gov.au/news-and-media/4112019-have-your-say-boo-park-community-facility
Have your say on the potential community facility at your precinct or on My Say Freo. To find out more click here or visit: mysay.fremantle.wa.gov.au/community-facility
Consultation has concludedAs part of the High Street project Main Roads will fund a program of accommodation works including the temporary reconfiguration of the golf course to ensure it can remain open for the majority of the construction period and some long term improvements, including the permanent realignment and redesign of the course, a new club house and a suitable replacement for the community facility.
The council’s Finance, Policy, Operations and Legislation Committee has authorised City officers to progress with the design of a co-located clubhouse and community facility.
View the full media release by clicking here or visiting: www.fremantle.wa.gov.au/news-and-media/4112019-have-your-say-boo-park-community-facility
Have your say on the potential community facility at your precinct or on My Say Freo. To find out more click here or visit: mysay.fremantle.wa.gov.au/community-facility
-
Infographic Released by Main Roads
Share Infographic Released by Main Roads on Facebook Share Infographic Released by Main Roads on Twitter Share Infographic Released by Main Roads on Linkedin Email Infographic Released by Main Roads link
Main Roads WA have released an infographic on the impact of the project on established trees. You can view the infographic here: project.mainroads.wa.gov.au/home/Documents/High%20Street%20Infographic%20-%20FINAL%20(002).pdfConsultation has concluded
Main Roads WA have released an infographic on the impact of the project on established trees. You can view the infographic here: project.mainroads.wa.gov.au/home/Documents/High%20Street%20Infographic%20-%20FINAL%20(002).pdf -
Environmental Protection Authority Grants Approval
Share Environmental Protection Authority Grants Approval on Facebook Share Environmental Protection Authority Grants Approval on Twitter Share Environmental Protection Authority Grants Approval on Linkedin Email Environmental Protection Authority Grants Approval linkThe Main Roads WA High St Upgrade was approved by the EPA on 23 May 2019.
For more information on this project and to read the Ministerial Statement including diagrams of trees to be retained and cleared, as well the placement of noise walls, please visit the EPA website: www.epa.wa.gov.au/proposals/high-street-upgrade
Consultation has concludedThe Main Roads WA High St Upgrade was approved by the EPA on 23 May 2019.
For more information on this project and to read the Ministerial Statement including diagrams of trees to be retained and cleared, as well the placement of noise walls, please visit the EPA website: www.epa.wa.gov.au/proposals/high-street-upgrade
-
Updated concept plan released
Share Updated concept plan released on Facebook Share Updated concept plan released on Twitter Share Updated concept plan released on Linkedin Email Updated concept plan released linkMain Roads WA have updated the concept plan for the proposed High Street upgrade.
The revised plan includes:
- two new underpasses at the junctions of Forrest Street and Stirling Highway and Montreal Street and High Street.
- changes to the roundabout design, including a new bypass lane for vehicles travelling west into Fremantle and a new slip lane for vehicles from Fremantle travelling north to Stirling Highway.
More information on the updated concept plan is available in the newsletter below.
Main Roads WA Newsletter High Street Upgrade (August 2018)
Consultation has concludedMain Roads WA have updated the concept plan for the proposed High Street upgrade.
The revised plan includes:
- two new underpasses at the junctions of Forrest Street and Stirling Highway and Montreal Street and High Street.
- changes to the roundabout design, including a new bypass lane for vehicles travelling west into Fremantle and a new slip lane for vehicles from Fremantle travelling north to Stirling Highway.
More information on the updated concept plan is available in the newsletter below.
Main Roads WA Newsletter High Street Upgrade (August 2018)
-
Community engagement concluded
Share Community engagement concluded on Facebook Share Community engagement concluded on Twitter Share Community engagement concluded on Linkedin Email Community engagement concluded linkOver 200 submissions were received by Main Roads WA on the High Street Upgrade - Stirling Highway to Carrington Street.
The feedback is currently under review and will inform and refine the concept design.
This is expected to be completed late 2018.
A summary of the community feedback is available below.
High Street Upgrade Community Feedback Summary
If you have any further questions, please email highstreetupgrade@mainroads.wa.gov.au or call138 138.
Consultation has concludedOver 200 submissions were received by Main Roads WA on the High Street Upgrade - Stirling Highway to Carrington Street.
The feedback is currently under review and will inform and refine the concept design.
This is expected to be completed late 2018.
A summary of the community feedback is available below.
High Street Upgrade Community Feedback Summary
If you have any further questions, please email highstreetupgrade@mainroads.wa.gov.au or call138 138.
Timeline
-
Community feedback
Main Roads WA High Street Upgrade has finished this stageDraft concept plan is available for draft comment
19 April – 31 May 2018
-
Concept design phase
Main Roads WA High Street Upgrade has finished this stageComments and feedback will be considered by the project team. Project updates, including the outcomes of the community engagement will be made available.
June – November 2018
-
EPA application
Main Roads WA High Street Upgrade has finished this stage2018/2019
-
Works contract
Main Roads WA High Street Upgrade has finished this stageMRWA expect to receive costed proposals in July and a contract for the delivery of the High Street Upgrade project is on track to be awarded in November 2019.
2019
-
Construction commences
Main Roads WA High Street Upgrade is currently at this stageMRWA will advise when construction expected to begin.
Anticipated early 2020.
Contact Main Roads WA
-