We're planning to upgrade six intersections on South Terrace to slow traffic and help create a pedestrian friendly environment that supports street life.
Each intersection 'node' will include:
Reduced road width to make it safer for people to cross the street.
Removing and replacing temporary speed bumps with a raised platform, surfaced with red asphalt and stencil markings to delineate the section and encourage drivers to slow down.
Widened footpath to create a bigger pedestrian area.
New paving, street furniture and trees to create a better space for people.
A map of the proposed works between Douro Road and South Street and the proposed order of completion can be downloaded here or refer to the timeline on this page.
Node two (Jenkin Street / South Terrace)
With node one (Little Lefroy Lane) and in-ground drainage works for node two (Jenkin Street) both complete, the streetscape component for node two has now received budget approval. The design inspiration for node two will be the mosaic located outside the Meeting Place, part of a community-led bush tucker art project launched in 2008. An early artists impression is included below and you can see the mosaic on the footpath outside the Meeting Place. Detailed streetscape design, incorporating this mosaic inspired artwork, will be shared in further updates.
For more information about this project please read the FAQs and timeline on this page.
We're planning to upgrade six intersections on South Terrace to slow traffic and help create a pedestrian friendly environment that supports street life.
Each intersection 'node' will include:
Reduced road width to make it safer for people to cross the street.
Removing and replacing temporary speed bumps with a raised platform, surfaced with red asphalt and stencil markings to delineate the section and encourage drivers to slow down.
Widened footpath to create a bigger pedestrian area.
New paving, street furniture and trees to create a better space for people.
A map of the proposed works between Douro Road and South Street and the proposed order of completion can be downloaded here or refer to the timeline on this page.
Node two (Jenkin Street / South Terrace)
With node one (Little Lefroy Lane) and in-ground drainage works for node two (Jenkin Street) both complete, the streetscape component for node two has now received budget approval. The design inspiration for node two will be the mosaic located outside the Meeting Place, part of a community-led bush tucker art project launched in 2008. An early artists impression is included below and you can see the mosaic on the footpath outside the Meeting Place. Detailed streetscape design, incorporating this mosaic inspired artwork, will be shared in further updates.
For more information about this project please read the FAQs and timeline on this page.
Join the South Terrace Streetscape Improvement mailing list here.
Timeline (South Terrace)
Node 1 - between Little Lefroy & Sydney St
South Terrace streetscape improvement has finished this stage
Development of draft concept, community engagement,
Council and Main Roads WA approval, construction
August - November 2018
Node 2 - Jenkin St
South Terrace streetscape improvement has finished this stage
Community feedback on node one and ideas for node two.
Planning, development and site-specific consultation on node one.
Late 2018 - Early 2019
New pipework, replacement of damaged soak wells and installation of new drains, in preparation for above ground works.
May - June 2019
Area 1 - Resurfacing
South Terrace streetscape improvement has finished this stage
Road resurfacing on South Terrace from South Street to completed node 1 at Little Lefroy Lane. Includes buildouts at intersections to improve sightlines, planting of new trees and replacement of old footpath with new.
May - June 2020
Node 2 - Jenkin St (streetscape)
South Terrace streetscape improvement is currently at this stage
Detailed design, engagement, planning and construction.
October 2021
Area 2 - Resurfacing
this is an upcoming stage for South Terrace streetscape improvement
Road resurfacing on South Terrace from Douro Road to completed node 2 at Jenkin St.
2021/22
Node 3 - Scott St
this is an upcoming stage for South Terrace streetscape improvement
Date TBC
Node 4 - Charles St
this is an upcoming stage for South Terrace streetscape improvement
Date TBC
Node 5 - Nelson St
this is an upcoming stage for South Terrace streetscape improvement
Date TBC
Node 6 - Orient St
this is an upcoming stage for South Terrace streetscape improvement